POWER: Capacity on 350MW Estlink 1 To Be Lowered Over 8-10 Feb Amid Iso Testing

Feb-06 13:55

Capacity on the 350MW Estlink 1 power cable between Finland-Estonian will be reduced to 150MW over 8-10 February due to the Baltic isolation test over the period, latest Remit data show.

  • Capacity on the link will drop to 248MW on 8 February between 00:00-01:00CET before being lowered to 150MW over 01:00CET 8 February and 10 February 00:00CET.
  • The test is done to ensure Baltic frequency stability ahead of synchronisation with the EU grid on 9 February.
  • Capacity is lowered in both directions.
  • The 650MW Estlink 2 is still disconnected until 31 July.

Historical bullets

MNI: US REDBOOK: JAN STORE SALES +5.8% V YR AGO MO

Jan-07 13:55
  • MNI: US REDBOOK: JAN STORE SALES +5.8% V YR AGO MO
  • US REDBOOK: STORE SALES +6.8% WK ENDED JAN 04 V YR AGO WK

BONDS: US Tnotes fades from the lows

Jan-07 13:47
  • Mostly two way price action in Treasuries for the past 3 hours, latest flows sees buying interest albeit well within the session's range, and the longer part of the curves remain offered across the US, EU and UK.
  • TYH5 is bought in 3k, TUA 2k, and USA 1.2k, but 372k lots traded in Tnotes is very low for this time of the day as Desks await the US Data in just over an Hour.

MNI EXCLUSIVE: Chinese Policy Advisors And Traders On Yuan Outlook

Jan-07 13:33

MNI speaks to Chinese policy advisors and traders about the outlook for the yuan. -On MNI Policy MainWire now, for more details please contact sales@marketnews.com