PBF Energy is planning turnarounds at four of its refineries in 2024 according to the firm’s 2024 guidance.
- The firm will shut the FCC at its 171k b/d Delaware City, Delaware, refinery in 1Q for 40-50 days.
- The 173k b/d Toledo, Ohio, refinery will shut a hydrocracker, crude unit and UDEX unit in 1Q for 40-50 days.
- PBF’s 156k b/d Martinez refinery near San Francisco will shut a hydrocracker in 2Q for 40-50 days.
- The 190k b/d Chalmette refinery on the Mississippi River east of New Orleans will shut an FCC and an alkylation unit in 4Q for 40-50 days.