Citgo’s 455kb/d Lake Charles refinery in southwest Louisiana is to start a multiunit turnaround beginning in late February according to Bloomberg sources.

  • The staggered maintenance, with units shutting and restarting at different times, is expected to continue until the fourth week of April.
  • One of three fluid catalytic crackers, the 50kb/d FCC-A, will be offline from late February through to late April.
  • The turnaround includes works on two reformers, a naphtha hydrotreater and Crude Topper C and one of four crude distillation units.

REFINING: Citgo Lake Charles Refinery Multiunit Turnaround from Feb to Apr

Last updated at:Jan-25 13:12By: David Lee
US

Citgo’s 455kb/d Lake Charles refinery in southwest Louisiana is to start a multiunit turnaround beginning in late February according to Bloomberg sources.

  • The staggered maintenance, with units shutting and restarting at different times, is expected to continue until the fourth week of April.
  • One of three fluid catalytic crackers, the 50kb/d FCC-A, will be offline from late February through to late April.
  • The turnaround includes works on two reformers, a naphtha hydrotreater and Crude Topper C and one of four crude distillation units.